Back
Quantor hybrid hydraulic PTO

PTO Stage 3 - Public Report - Artemis Intelligent Power Ltd


  • Stage

    Stage 3

  • Project Lead

    Artemis Intelligent Power Ltd

  • Project Sub-Contractors

    Quoceant Ltd

  • Author

    Artemis Intelligent Power Ltd

  • Date

    February 2020

This is the PTO Stage 3 summary report for the Artemis Intelligent Power Ltd project.

Included within this public report is a high level overview of the technology, and the activities completed on the Quantor PTO project during Stage 3.

Features include an overview of the scope of work completed, the project achievements, lessons learnt, and recommendations for future work. The project performance against key metrics is also presented.

Project Keywords: LCOE, Lessons Learnt, Metrics, Generator, Modelling, Simulation, Testing, Hydraulics, Stage 3, PTO