Pelamis Cost Metrics

High Level Cost Metrics for WEC Machine Elements


  • Project Lead

    Quoceant Ltd

  • Author

    Quoceant Ltd

  • Date

    April 2016

The cost metrics presented throughout this document are derived or estimated from known Pelamis P2 costs for components that were selected based on optimising the Levelised Cost of Energy (LCoE) for the Pelamis as a whole. 

All of the costs included in this document are discussed in more detail in the relevant cost metrics reports:

  • PTO Cost Metrics covers PTO system costs as well as costs associated with the main structural elements
  • Mooring & Connection Systems Cost Metrics provides further information on the basis of the moorings and electrical infrastructure costs.

The lowest up-front cost of components does not necessarily lead to the most commercially beneficial project and so a balance must be achieved. For example, doubling up on component to provide redundancy and fault tolerance may provide huge cost savings over the life of the project due to increased availability. 

The additional drivers, as well as cost, that need to be considered when selecting components include:

  • WEC availability
  • Reliability
  • PTO efficiency
  • Power Capture
  • Impact on O&M costs and strategy. 

Separate pages detail cost metrics and costs in their most practical form for individual components, systems, assemblies, or component types within the following sub-systems:

  • Pelamis Main Structural Components
  • PTO Primary Transmission Components
  • PTO Energy Storage Components
  • PTO Secondary Transmission Components
  • Miscellaneous Additional Components
  • Mechanical Mooring Components
  • SubSea Electrical Infrastructure

 

Additional reports, documents and data files referenced here may not be publicly available.

Pricing details were accurate at the time of writing in 2015, but should now be considered out of date. Supplier names have been redacted. 

Other reports from this

NWEC Stage 1 - Public Report - Quoceant Ltd

NWEC stage 1 project summary report for the Quoceant Automatically Inflatable and Stowable Volume (AISV) project. Includes a description of the technology, scope of work, achievements and recommendations for further work.

View Details

SMMP Stage 1 - Public Report - Quoceant

SMMP stage 1 project summary report for the Quoceant Advanced Concrete Engineering ‐ WEC (ACE‐WEC) project. Includes a description of the technology, scope of work, achievements and recommendations for further work.

View Details