Pelamis PTO System Cost Metrics
Detailed breakdown of component costs within the PTO system of the Pelamis P2 machine procured in 2010, and tested over a number of years at EMEC.
The cost metrics presented throughout this document are derived or estimated from known Pelamis P2 costs for components that were selected based on optimising the Levelised Cost of Energy (LCoE) for the Pelamis as a whole.
All of the costs included in this document are discussed in more detail in the relevant cost metrics reports:
The lowest up-front cost of components does not necessarily lead to the most commercially beneficial project and so a balance must be achieved. For example, doubling up on component to provide redundancy and fault tolerance may provide huge cost savings over the life of the project due to increased availability.
The additional drivers, as well as cost, that need to be considered when selecting components include:
Separate pages detail cost metrics and costs in their most practical form for individual components, systems, assemblies, or component types within the following sub-systems:
Additional reports, documents and data files referenced here may not be publicly available.
Pricing details were accurate at the time of writing in 2015, but should now be considered out of date. Supplier names have been redacted.
Detailed breakdown of component costs within the PTO system of the Pelamis P2 machine procured in 2010, and tested over a number of years at EMEC.
The Pelamis machine included a novel system allowing rapid connect/disconnect from both the mooring system and electrical cable simultaneously. Cost breakdown for this system is given.
A summary of the reports contained within the 5 work packages of Project Secure.
Set of reports detailing the sophisticated hydraulic power take off system used in the large scale Pelamis prototypes
Detailed reports on the mooring and connection system designed by Pelamis for their large scale prototypes
The PELs suite of custom Pelamis simulation software is covered in this set of reports
Conclusions and recommendations are given based on the Pelamis cost of energy modelling
Detailed breakdown of component costs within the PTO system of the Pelamis P2 machine procured in 2010, and tested over a number of years at EMEC.
The Pelamis machine included a novel system allowing rapid connect/disconnect from both the mooring system and electrical cable simultaneously. Cost breakdown for this system is given.
NWEC stage 1 project summary report for the Quoceant Automatically Inflatable and Stowable Volume (AISV) project. Includes a description of the technology, scope of work, achievements and recommendations for further work.
SMMP stage 1 project summary report for the Quoceant Advanced Concrete Engineering ‐ WEC (ACE‐WEC) project. Includes a description of the technology, scope of work, achievements and recommendations for further work.
This additional Controls documentation provides a condensed background description of Power Take Off modelling requirements, and Power Take Off specifications for control systems developers.
A summary of the Q-Connect technology, and the scope of work, outcomes, and next steps for development that were identified during Stage 1.
A summary of the Q-Connect technology, and the scope of work, outcomes, and next steps for development that were identified during Stage 2.