Pelamis Cost Metrics

Moorings and Connection Systems Cost Metrics


  • Project Lead

    Quoceant Ltd

  • Author

    Quoceant Ltd

  • Date

    July 2015

This report looks at the Pelamis P2 mooring system and the cost metrics associated with the major components therein. The P2 mooring system was a chain based catenary spread incorporating electrical export and communication components.

The catenary mooring system utilised standard embedment anchors, with chain lines on the sea bed to give the required spring force, and synthetic tethers rising up through the water column to the machine connection point. The necessary equipment to enable the rapid connection and disconnection of the Pelamis WEC to/from its moorings was located at this connection point. This connection point included a remotely operated locking system to allow both mooring and electrical connections to be made in a single unit. The Tether Latch Assembly (TLA) costs are broken down to show elements including the wet-mate connector, dynamic cable and mechanical components.

The majority of costs used in this report are those for moorings components for the P2 mooring spreads deployed at the EMEC site in Orkney in 2010 and 2011 with the actual purchases being made from 2009 onwards. Some items in the system were replaced over the course of the P2 operations programme, procured as spares, or for ongoing operations and these later costs have been included if appropriate.
Each major component in the Pelamis mooring system is considered in the document and the most appropriate cost metric for that component defined. Appropriate metrics for each of the major components are then brought together to provide example costings for three indicative systems, namely;

  • Single device with passive yaw system
  • Single device with active yaw system
  • 10 machine farm with active yaw system

This report gives more context and description of the mooring and connection system costs in the High Level Cost Metrics report. 

 

 

Additional reports, documents and data files referenced here may not be publicly available.

Pricing details were accurate at the time of writing in 2015, but should now be considered out of date. Supplier names have been redacted. 

Other reports from this

NWEC Stage 1 - Public Report - Quoceant Ltd

NWEC stage 1 project summary report for the Quoceant Automatically Inflatable and Stowable Volume (AISV) project. Includes a description of the technology, scope of work, achievements and recommendations for further work.

View Details

SMMP Stage 1 - Public Report - Quoceant

SMMP stage 1 project summary report for the Quoceant Advanced Concrete Engineering ‐ WEC (ACE‐WEC) project. Includes a description of the technology, scope of work, achievements and recommendations for further work.

View Details