Pelamis High Level Cost Metrics
Breakdown of build costs for key components within the Pelamis P2 wave energy converter, procured and built in 2010/2011.
The Pelamis P2 hydraulic PTO system comprised three main parts: primary transmission, secondary transmission, and the energy storage that lay between them. This report details the assumptions, costs and some of the various options for the three system parts. The majority of the costs used in the analysis are the actual costs for the P2-002 machine procured in 2010, however some costs associated with the earlier P2-001 machine have been used where required.
Appropriate cost metrics are derived for each of the major components and their associated parts, and are presented throughout the document. For the primary PTO components, cost per unit weight or volume is likely the most relevant metric for each of the different types of technology described.
For the secondary PTO system, the cost per kW of electrical rated power is provided where possible or additional metrics such as cost per generator have been defined. In each section the scalability of the particular system in question has been discussed. Due to the modular nature of the energy storage and secondary systems, they lend themselves well to scaling up.
The cost breakdown includes hydraulic cylinders, manifolds and piping, control and instrumentation. Sample costs for a secondary PTO system of different electrical ratings ranging from 205kW to 1MW are also given.
This report gives more context and description to the PTO costs in the High Level Cost Metrics report.
Additional reports, documents and data files referenced here may not be publicly available.
Pricing details were accurate at the time of writing in 2015, but should now be considered out of date. Supplier names have been redacted.
Breakdown of build costs for key components within the Pelamis P2 wave energy converter, procured and built in 2010/2011.
The Pelamis machine included a novel system allowing rapid connect/disconnect from both the mooring system and electrical cable simultaneously. Cost breakdown for this system is given.
A summary of the reports contained within the 5 work packages of Project Secure.
Set of reports detailing the sophisticated hydraulic power take off system used in the large scale Pelamis prototypes
Detailed reports on the mooring and connection system designed by Pelamis for their large scale prototypes
The PELs suite of custom Pelamis simulation software is covered in this set of reports
Conclusions and recommendations are given based on the Pelamis cost of energy modelling
Breakdown of build costs for key components within the Pelamis P2 wave energy converter, procured and built in 2010/2011.
The Pelamis machine included a novel system allowing rapid connect/disconnect from both the mooring system and electrical cable simultaneously. Cost breakdown for this system is given.
NWEC stage 1 project summary report for the Quoceant Automatically Inflatable and Stowable Volume (AISV) project. Includes a description of the technology, scope of work, achievements and recommendations for further work.
SMMP stage 1 project summary report for the Quoceant Advanced Concrete Engineering ‐ WEC (ACE‐WEC) project. Includes a description of the technology, scope of work, achievements and recommendations for further work.
This additional Controls documentation provides a condensed background description of Power Take Off modelling requirements, and Power Take Off specifications for control systems developers.
A summary of the Q-Connect technology, and the scope of work, outcomes, and next steps for development that were identified during Stage 1.
A summary of the Q-Connect technology, and the scope of work, outcomes, and next steps for development that were identified during Stage 2.